Furnace Burner Management System (BMS) Upgrade

 

 

GCM's Mandate

Engineering, Procurement and Construction Management




The main objective of the project was to improve the overall reliability of the furnace, including replacement of the BMS unit c/w instrumentation, piping modifications, new building, and all procedures required to obtain CSA/RBQ approval.


GCM conducted the multidisciplinary engineering activities, including:

  • Final FEED report including project schedule and detailed cost estimate

  • Project planning

  • Detailed engineering in all disciplines

  • Functional descriptions for the combustion control system

  • Documentation required for approval by CSA/RBQ
    (Régie du bâtiment du Québec)

  • Procurement

  • Follow-up of deliveries

  • Construction work specifications

  • Preparation of pre-operational checks’ documents

  • Field technical assistance during construction

  • Monitoring and control of project costs and schedule

BNQ Certified System

Activity sectorsz

Oil and Gas Chemical and Petrochemical Mining and metals Renewable Energy Manufacturing Pharma, Biotech and Food Environment and Sustainable Development

You want to be a part of our team?

We are always looking for new talent!


See the available offers


OR

Send a
personalized application