Nitric Acid Tank Relocation

Alberta, Canada

Nitric Acid Tank Relocation

 

Project

Relocation of Two Nitric Acid Storage Tanks

 

GCM Mandate

Engineering, Procurement and Construction Management




GCM performed the multidisciplinary engineering (FED-1-2 and detailed) for the whole project, including:

  • Concept Development
  • Detailed Project Cost Estimate
  • Relocation of roads and site layout rearrangement
  • Design of dykes, equipment foundations, tank supports, piles, drainage, platform structures, pipe racks and pump monorails, etc.
  • Specifications of pumps, piping design and relocation, new emergency shower
  • All E&I work related to the modifications
  • Procurement and implementation strategies
  • All work specifications (Demolition and New Installations)
  • Monitoring and control of Costs and Schedule
  • Field assistance during Construction
BNQ Certified System

Activity sectorsz

Oil and Gas Chemical and Petrochemical Mining and metals Energy Manufacturing Pharma, Biotech and Food Environment and Sustainable Development

You want to be a part of our team?

We are always looking for new talent!


See the available offers


OR

Send a
personalized application