Modernization at the Water Treatment Unit

Quebec, Canada

Modernization at the Water Treatment Unit

Project

Biological Treatment Restoration

 

GCM Mandate

Engineering, Procurement and Construction Management




The main objective of the project was to restore the biological treatment at the Montréal Refinery in order not to exceed the BOD5 limits and to maintain the ISO14001 certification. The project consists in the installation of a new concrete basin, which serves as a bioreactor, air agitation blowers including new shelter, phosphoric acid injection module, piping modifications, electricity and instrumentation.

 

GCM conducts the multidisciplinary engineering activities, including: 

 

 

  • Final FEED report including project schedule and detailed cost estimate
  • Project planning
  • Detailed engineering in all disciplines
  • Procurement
  • Follow-up on deliveries
  • Construction work specifications
  • Preparation of pre-operational check documents
  • Field technical assistance during construction
  • Monitoring and control of project costs and schedule
BNQ Certified System

Activity sectorsz

Oil and Gas Chemical and Petrochemical Mining and metals Energy Manufacturing Pharma, Biotech and Food Environment and Sustainable Development

You want to be a part of our team?

We are always looking for new talent!


See the available offers