Tire manufacturing plant expansion
Québec, Canada
Project description
The project consisted of installing a fourth production line in the existing plant and upgrading the cooling water system.
Total project cost
$15M
GCM Mandate
Detailed mechanical and automation engineering for the expansion and multidisciplinary engineering for the cooling tower installation.
Deliverables
- Detailed engineering, all disciplines
- Project cost estimate (+/30%)
- Detailed scheduling and planning
- Construction supervision